Docket No. ER18-1307-000 1

FEDERAL ENERGY REGULATORY COMMISSION

WASHINGTON, DC 20426

 

OFFICE OF ENERGY MARKET REGULATION

 

New York Independent System         

  Operator, Inc.

Docket No. ER18-1307-000

 

Issued:  5/9/18

 

New York Independent System Operator, Inc.

10 Krey Boulevard

Rensselaer, NY 12144

 

Attention:Garrett E. Bissell

Senior Attorney

 

Reference:Informational Calculations Related to Net Congestion Rent Settlements

 

Dear Mr. Bissell:

 

              On April 6, 2018, New York Independent System Operator, Inc. (NYISO) submitted revisions to Attachment N of its Open Access Transmission Tariff.[1]  NYISO states that these revisions modify the current requirement to annually perform certain informational calculations related to Day-Ahead Market Net Congestion Rent settlements.[2]

              Pursuant to the authority delegated to the Director, Division of Electric Power Regulation – East, under 18 C.F.R. § 375.307 (2017), your submittal is accepted for filing, effective June 6, 2018, as requested.

              The filing was noticed on April 6, 2018, with comments, interventions, and protests due on or before April 27, 2018.  Pursuant to Rule 214 (18 C.F.R. 385.214 (2017)), to the extent that any timely filed motions to intervene and any motion to intervene out-of-time were filed before the issuance date of this order, such interventions are granted.  Granting late interventions at this stage of the proceeding will not disrupt the proceeding or place additional burdens on existing parties.

              This acceptance for filing shall not be construed as constituting approval of the referenced filing or of any rate, charge, classification, or any rule, regulation, or practice affecting such rate or service contained in your filing; nor shall such acceptance be deemed as recognition of any claimed contractual right or obligation associated therewith; and such acceptance is without prejudice to any findings or orders which have been or may hereafter be made by the Commission in any proceeding now pending or hereafter instituted by or against NYISO.

              This order constitutes final agency action.  Requests for rehearing by the Commission may be filed within 30 days of the date of issuance of this order, pursuant to 18 C.F.R. § 385.713 (2017).

 

Sincerely,

 

 

Kurt M. Longo, Director

Division of Electric Power Regulation – East

 

 


[1] New York Independent System Operator, Inc., NYISO Tariffs, NYISO OATT, 20.2 OATT Att N Congestion Settlements Related to the Day-Ah, 5.0.0.