Docket No. ER13-1390-0002
FEDERAL ENERGY REGULATORY COMMISSION
WASHINGTON, D.C. 20426
OFFICE OF ENERGY MARKET REGULATION
New York Independent System Operator, Inc.
Docket No. ER13-1390-000
Issued: 6/14/13
New York Independent System Operator, Inc.
10 Krey Boulevard
Rensselaer, NY 12144
National Grid USA Service Company, Inc.
40 Sylvan Road
Waltham, MA 02451
Attention:Sara B. Keegan
Counsel for the New York Independent System Operator, Inc.
Amanda C. Downey
Counsel for National Grid USA Service Company, Inc.
Reference:Large Generator Interconnection Agreement
Dear Ms. Downey:
On May 1, 2013, New York Independent System Operator, Inc. (NYISO) and Niagara Mohawk Power Corporation d/b/a National Grid (National Grid) (collectively, the Filing Parties) submitted an executed Large Generator Interconnection Agreement (LGIA) among the NYISO, National Grid, and Erie Boulevard Hydropower, LP (Erie Blvd. Hydro).[1]
Pursuant to the authority delegated to the Director, Division of Electric Power
Regulation – East, under 18 C.F.R. §375.307, your submittal is accepted for filing, effective April 17, 2013, as requested.
The filing was noticed on May 2, 2013, with comments, interventions and protests due on or before May 22, 2013. Pursuant to Rule 214 (18 C.F.R. § 385.214 (2013)), to the extent that any timely filed motions to intervene and any motion to intervene out-of-time were filed before the issuance date of this order, such interventions are granted. Granting late interventions at this stage of the proceeding will not disrupt the proceeding or place additional burdens on existing parties.
This acceptance for filing shall not be construed as constituting approval of the referenced filing or of any rate, charge, classification, or any rule, regulation, or practice affecting such rate or service contained in your filing; nor shall such acceptance be deemed as recognition of any claimed contractual right or obligation associated therewith; and such acceptance is without prejudice to any findings or orders which have been or may hereafter be made by the Commission in any proceeding now pending or hereafter instituted by or against NYISO or National Grid.
This order constitutes final agency action. Requests for rehearing by the Commission may be filed within 30 days of the date of issuance of this order, pursuant to 18 C.F.R. § 385.713.
Sincerely,