UNITED STATES OF AMERICA
FEDERAL ENERGY REGULATORY COMMISSION
Marble River, LLC
Noble Clinton Windpark I, LLC
Noble Ellenburg Windpark, LLC
Noble Chateaugay Windpark, LLC
New York Independent System Operator, Inc.
NOTICE SHORTENING ANSWER PERIOD
(January 24, 2013)
On January 23, 2013, Marble River, LLC, Noble Clinton Windpark I, LLC, Noble Ellenburg Windpark, LLC, Noble Chateaugay Windpark, LLC, and New York Independent System Operator, Inc. (collectively, Parties) filed a joint motion for an additional deferral of the comment period (motion), from January 25, 2013, to February 8, 2013, in the above-referenced proceeding. In addition, the Parties request the Commission act expeditiously on the motion.
Upon consideration, notice is hereby given that the date for filing answers to the Parties’ motion is shortened to and including January 24, 2013.
Kimberly D. Bose,
Secretary.