137 FERC ¶ 61,229

UNITED STATES OF AMERICA

FEDERAL ENERGY REGULATORY COMMISSION

 

Before Commissioners:  Jon Wellinghoff, Chairman;

Philip D. Moeller, John R. Norris,

and Cheryl A. LaFleur.

 

New York Independent System Operator, Inc.Docket No. ER04-449-024

 

ORDER ON CLARIFICATION
(Issued December 19, 2011)

1. The New York Independent System Operator (NYISO) administers the Installed Capacity (ICAP) market in the New York Control Area (NYCA).  In this order the
Commission grants clarification of its September 8, 2011 order1 which, inter alia,
accepted, in part, and rejected, in part, proposed criteria that would govern the evaluation and potential creation of new ICAP zones.

Background

2. The ICAP market uses NYISO-determined demand curves for each of three ICAP
pricing zones; NYCA (or Rest-of-State), New York City (NYC, comprised of load zone

J), and Long Island (LI, comprised of load zone K).  The NYC and LI capacity zones are referred to as “locational” zones because they each have a separate requirement that a certain minimum percentage of the zone’s required generating capacity must be
physically located within that zone.

 

 

 

 

 

1 New York Indep. Sys. Operator, Inc., 136 FERC ¶ 61,165 (2011) (September 8, 2011 Order).


 

 

Docket No. ER04-449-024- 2 -

 

3. As part of its implementation of the 2007 Consensus Deliverability Plan2

submitted to comply with the interconnection requirements of Order No. 2003,3 NYISO proposed that “NYISO staff and market participants will work collaboratively to develop over the next three years criteria for the potential formation of additional locational ICAP zones.”4  On January 4, 2011, NYISO and the New York Transmission Owners
(NYTOs)5 filed proposed Criteria and Considerations that would govern the evaluation and potential creation of new ICAP zones in NYCA.

4. In the September 8, 2011 Order, the Commission accepted the proposed Criteria
subject to modification, rejected the proposed Considerations, and directed NYISO to file
tariff revisions that implement the approved Criteria within 60 days of the date of the
order.6  In particular, as relevant here, the Commission agreed with protestors that the
NYISO proposal was not just and reasonable because it failed to adequately recognize
binding transmission constraints in the capacity market.  The Commission found that:

NYISO should use the methodology contained in the existing Attachment S
Deliverability Test in section 25.7.8 of Attachment S to the NYISO [Open
Access Transmission Tariff] in determining whether to create new zones.
That is, a new zone should be created when the total transmission transfer
capability (including any upgrades that would be required to be built to

 

2 See NYISO and the New York Transmission Owners, Consensus Deliverability
Plan, Docket No. ER04-449-003, et al. (filed October 5, 2007) (Consensus Deliverability
Plan).

3 Standardization of Generator Interconnection Agreements and Procedures,

Order No. 2003, FERC Stats. & Regs. ¶ 31,146 (2003), order on reh’g, Order No. 2003-
A, FERC Stats. & Regs. ¶ 31,160, order on reh’g, Order No. 2003-B, FERC Stats. & Regs. ¶ 31,171 (2004), order on reh’g, Order No. 2003-C, FERC Stats. & Regs. ¶ 31,190 (2005), aff'd sub nom. Nat’l Ass’n of Regulatory Util. Comm’rs v. FERC, 475 F.3d 1277 (D.C. Cir. 2007), cert. denied, 552 U.S. 1230 (2008).

4 Consensus Deliverability Plan at P 19.

5 The NYTOs are Central Hudson Gas & Electric Corporation, Consolidated
Edison Company of New York, Inc., Long Island Power Authority, New York Power
Authority, New York State Electric & Gas Corporation, Orange & Rockland Utilities,
Inc., Rochester Gas and Electric Corporation, and Niagara Mohawk Power Corporation.

6 For a more detailed discussion of the Criteria and Considerations, see September 8, 2011 Order, 136 FERC ¶ 61,165 at P 4-7.


 

 

Docket No. ER04-449-024- 3 -

 

make new resources capacity-qualified) is insufficient to allow all of the

capacity resources in a pre-existing zone to be deliverable throughout the

pre-existing zone.7

5.On October 11, 2011, NYISO filed a request for clarification or, in the alternative,

rehearing of the September 8, 2011 Order.

Request for Clarification or, in the Alternative, Rehearing

6. NYISO requests clarification of paragraph 52 of the September 8, 2011 Order,
which directs NYISO to use the methodology contained in the existing Attachment S
Deliverability Test in section 25.7.8 of Attachment S to the NYISO OATT in
determining whether to create new zones.  NYISO states that section 25.7.8 sets forth the
deliverability test methodology that NYISO uses to determine the capacity deliverability
of class year projects8 over Highway facilities and Byway facilities9 (Deliverability
Test10) , but it also contains, in subsection 25.7.8.2.14, criteria to perform an additional
assessment of the aggregate system impact of class year projects on Highway facilities
(the “Project Impact Assessment”).  NYISO states that only the application of the
Deliverability Test methodology to Highway facilities is relevant to the consideration of
new capacity zones, for the reasons discussed below.  NYISO requests that the
Commission clarify that the directive to use the “existing Attachment S Deliverability
Test in section 25.7.8” is intended to require NYISO to propose compliance tariff
modifications that provide that the Deliverability Test in section 25.7.8 will be applied to

 

7 September 8, 2011 Order, 136 FERC ¶ 61,165 at P 52.

8 Class year projects consist of the group of projects that make up the Annual
Transmission Reliability Assessment and Class Year Deliverability Study for new
interconnection projects conducted in accordance Attachment S of the NYISO OATT.

9 NYISO states that, as defined in Attachment S of the NYISO OATT, Highway
facilities are the major transmission interfaces between the nine Load Zones within the
currently defined Rest-of-State capacity region, and include, as immediately connected,
in series, Bulk Power facilities in New York State, whereas Byway facilities are those
transmission facilities that are neither Highways nor Other Interfaces.  NYISO October
11, 2011 Filing at 4-5.  See NYISO OATT, Attachment S, section 25.1.2.  All

transmission facilities in NYISO Zones J and K are defined as Byways.  Id.

10 NYISO defines deliverability as the ability to deliver the aggregate of NYCA capacity resources to the aggregate of the NYCA load under summer peak conditions. See section 25.7.8.1 of Attachment S to the NYISO OATT.


 

 

Docket No. ER04-449-024- 4 -

 

Highway facilities to determine whether constraints exist that warrant the creation of new capacity zones.

7. NYISO contends that this understanding of the September 8, 2011 Order is

consistent with the Market Monitoring Unit’s (MMU) comments11 and no other party to
the proceeding proposed that the new capacity zone analysis utilize the assessment of
Byway facilities.  Further, according to NYISO, this exclusive application of the
Deliverability Test methodology to Highway facilities is consistent with the
Commission’s acceptance of NYISO’s proposal to evaluate whether to establish new
capacity zones with the same boundaries as existing NYCA load zones.12  NYISO adds
that the assessment of Highway facilities by applying the Deliverability Test
methodology in section 25.7.8 will provide the information necessary to determine
whether inter-zonal constraints exist necessitating the creation of new Capacity zones
while the assessment of Byway facilities would not provide an indication of whether the
transmission system interfaces between load zones are constrained.

8. NYISO also requests clarification that the Commission did not intend to require the application of the Project Impact Assessment, which is contained in the last
subsection of section 25.7.8 of Attachment S.  NYISO argues that the Project Impact
Assessment is not intended to identify whether there are constraints between load zones but rather is a comparative analysis performed to determine whether proposed projects reduce the transfer capability of Highways when compared against a defined baseline
system.  According to NYISO, the test is only meaningful when identifying the impact of a particular project or group of projects on the transfer capability of Highways, and as
such, is not useful in identifying constraints between load zones and should not be
required when evaluating the need for a new capacity zone.

9. NYISO states that, in the alternative, it requests rehearing because the
Commission erred to the extent it is intending to require NYISO to perform all
assessments that are part of section 25.7.8 of OATT Attachment S because those
assessments provide no information necessary to the determination of whether new
capacity zones should be created.  Also, according to NYISO, reading paragraph 52 of
the September 8, 2011 Order to require NYISO to assess Byway facilities would make
the September 8, 2011 Order internally inconsistent because the Commission accepted
NYISO’s proposal to create new capacity zones that are concurrent with existing load

 

11 NYISO October 11, 2011 Filing at 4 (citing MMU Comments, Docket No. ER04-449-022 (filed January 25, 2011)).

12 NYISO October 11, 2011 Filing at 4 (citing September 8, 2011 Order, 136 FERC ¶ 61,165 at P 66).


 

 

Docket No. ER04-449-024- 5 -

 

zones.  NYISO states that, the Commission has acknowledged that currently the

administrative and developmental costs that would be incurred to implement sub-zonal capacity zones outweigh the benefits.

Commission Determination

10. We grant clarification that the section 25.7.8 Highway Capacity Deliverability
Test methodology to be used in the context of determining whether a new capacity zone
is needed should only be that test in section 25.7.8 which applies to Highway facilities.

11. We grant NYISO’s requested clarification because the discussion of the new

capacity zone determination in the September 8, 2011 Order pertained solely to Highway
facilities, as indeed noted by the heading of the section of the order to which NYISO
refers—IV.B.1.a. Highway Capacity Deliverability Test.  As NYISO states, new capacity
zones, when established, are based on the configuration of the existing load zones and the
evaluation of the major transmission interfaces that link the load zones, which are by
definition Highway facilities.  We agree with NYISO that the evaluation of Byways in
this context is not relevant to the evaluation of new capacity zones that use the same
boundaries as NYISO’s existing load zones.  Further, the impact assessment to which
NYISO refers is used to determine whether class year projects degrade interface transfer
capability as compared to a baseline.  We agree that this assessment is not useful in
identifying zonal constraints between the 11 load zones.  As NYISO points out, the
Commission found that the purpose of creating new capacity zones is to enable selection
and pricing of capacity considering all constraints that exist.13  Neither the Byway
evaluations nor the impact assessment are useful for the purpose of identifying
constraints between the 11 load zones.  Accordingly we agree with NYISO that only the
Highway application of the section 25.7.8 deliverability test methodology is necessary in
determining whether to create new zones from the existing load zones.14

12. Therefore, while certain of the provisions of section 25.7.8 set forth that NYISO
shall evaluate Byways and shall also conduct tests including an impact assessment, we
confirm that these provisions are not relevant to the discussion in the September 8, 2011
Order which pertains solely to the provisions of section 25.7.8 that concern Highway

 

13 September 8, 2011 Order, 136 FERC ¶ 61,165 at P 58.

14 We note that NYISO states that, if at some point in the future, in compliance

with the September 8, 2011 Order, existing Load Zones are to be subdivided, assessment of Byway facilities may be appropriate.  NYISO October 11, 2011 Filing at 5, note 17.
We are not asked to render a ruling on that issue here and will address it if and when it
arises in the future.


 

 

Docket No. ER04-449-024- 6 -

 

facilities in determining the need for new capacity zones.  Accordingly, we grant NYISO’s clarification request.

The Commission orders:

 

NYISO’s request for clarification is hereby granted, as discussed in the body of this order.

By the Commission. ( S E A L )

 

 

 

 

Kimberly D. Bose,
Secretary.